Hi Everyone,
We have recently implemented ChaRM with cCTS and I am having difficulty with a requirement from my development team. They have tools that they use for development that they want to be able to maintain in a single system and transport to all of the other development systems and all of the QA systems. I have been able to get this to work with TMS and using a transport group / transport layer, but when we create the transports through ChaRM, I am only given the option of a transport with a target of the QA system for the development system in which they are developing the code.
To be clear, we have 6 development systems in our project landscape, and 6 QA systems, and I want to develop in 1 of the development systems and have the transport release to a transport group containing the 5 other development systems and the 6 QA systems.
Does this seem like it should be possible with cCTS? Would it be possible if it were in a project without clustering active?